MainOne data centre power infrastructure
Material supply and installation of a 7.5MVA 33/11kV substation and eight 2000kVA 11/0.4kV distribution transformers.
- Client
- MainOne Data Company
- Location
- Ajah, Lagos
- Sector
- Data Centres
- Voltage class
- 33kV
- Status
- Commissioned
- Year
- 2015
Scope
What Caxten delivered
Material supply and installation of a 7.5MVA 33/11kV substation and eight 2000kVA 11/0.4kV distribution transformers.
The works were carried out by COREN-registered engineers under Caxten's safe systems of work, with test records, as-built documentation and handover certification issued to MainOne Data Company on completion.